Home > SI 2017 Documentation > User Guide > Projects > Project Explorer > Revisions / Change Orders > Compare Revisions

Compare Revisions

Table of contents

SI 2017 Page Logo.jpg

Details

 

The primary reason for creating Revisions is to be able to compare two Revisions of a Project and create a Change Order report.

Steps

 

  1. In the Project Explorer, select the Project whose Revisions you want to compare. Click the Revisions tab in the bottom section of the Project Explorer interface and click the [Compare] button:

 

compare button.png

 

  1. The Project Revision Comparer Selector form opens. Select the two Revisions you wish to compare. You can also choose whether you will just be comparing Price changes (most common) or both Price and Cost changes:

 

compare rev form.png

 

  1. The Project Compare Editor will open:

 

compare interface.png

 

This displays all of the changes between the two Revisions. In the example above there are Removed and Added Items. A third possibility would be Adjusted if you say, modified the price of an Item between the two Revisions. You can filter to any of these "Statuses" via the Change Status section:

 

File:SIX_Guide/007_Projects/001_Project_Explorer/Revisions/Compare_Revisions/change_status_section.jpg

 

You can run reports via the Reports tab. You can run any report against this comparison and there is also a specific Change Order report available:

 

change order report button.png

 

  1. Run a Change Order report and/or any other reports you wish to run

 

change order report sample.png

 

  1. Once a "Change Order" is accepted, you should create a Revision of the current project so that you can "lock down" a new comparison point for future change requests.

 