Home > SI 2018 Documentation > User Guide > Scheduling > Tasks > Managing Tasks

Managing Tasks

SI 2018 Page.png

Details

 

You can manage your Tasks via the Task Explorer:

 

manage tasks.png

 

task explorer.png

 

You can also view and manage Tasks via the Calendar or via the optional product Mobile Install.

Viewing Tasks

 

By default, all Tasks will display in the Task Explorer:

 

task explorer.png

 

You can filter your Tasks via the Quick Filter button:

 

quick filter.png

 

You can filter via the column filters:

 

column.png

 

You can also filter by Client and/or Project in the tree on the left side of the Task Explorer:

 

filter side.png

 

From the Project Explorer

 

When you have a Project selected in the Project Explorer, you can click the Tasks tab along the bottom section of the window:

 

project explorer.png

 

If you would like to see all of the Tasks for a Client and not just the ones for the selected Project, there is a check box for that:

 

show all tasks.png

Editing Tasks

 

You can edit multiple Tasks at a time using the Mass Update function on the ribbon:

 

mass update.png

 

You can choose which fields you want to update for the selected Tasks:

 

mass update fields.png

 

To edit an individual Task, you can double-click in the Task Explorer grid or you can select the Task and click the [Edit] button:

 

edit butt.png

 

This will open the task for edit. If a Task has been completed, you can change the Progress to "Completed":

 

completed.png

 

You can also change the "% Complete" field to 100%:

 

percent.png

 

If the Task is not completed, you can choose an appropriate Progress and % Complete if you wish.

 

You can also enter the Actual Hours on the Resources tab if you wish to track this:

 

act hours.png

 

When Actual Hours are entered, you can run the Task Labor Analysis and Task Labor Costing reports, see Task Reports.

 

To mark which Items were installed, click the Items tab and select the Items you want to mark as installed and click the [Update Install Status] button:

 

update inst stat.png

 

This will open a form where you can choose the Installed Date and and any Install Notes to the Item(s) selected:

 

update inst stat form.png

Project Fields Affected

 

When you use the Update Install Hours function for Items in a Task, those fields are updated for the Items within the Project the next time you open the Project Editor:

 

project fields updated.png

 

If for some reason, you don't want these fields to update, you can turn this function off in your Project Settings:

 

project settings tasks.png

Mobile Install Users

 

If you are using Mobile Install, Tasks will automatically update with the changes made in the Mobile Install interface. However, if you already have SI open when the changes are made in Mobile Install, you will need to click the [Update From] button in the Mobile Install section of the ribbon of the Task Explorer to bring down the changes:

 

manage tasks.png

 

 

update from.png

 

This will update the Task with information added within the Mobile Install web interface. You will get a confirmation once updated:

 

update task confirmation.png

 

You can now further edit the Task within SI 2018 if needed.

Site Items

 

If Site Items were added to the Task in the Mobile Install interface, click the Site Items tab in the Edit Task form:

 

site items tab.png

 

The next time you open the Project, you will be prompted to add the Site Items to the Project:

 

add site items.png

 

This will open a form where you can select the Site Items that you want to add to the Project. Click the [Add to Project] button:

 

add site items form.png

 

A form will open where you can select a Product from your Catalog, and choose the Location and System where you would like to assign the Product:

 

add products for site items.png

 

Once added, you will be prompted to save and check in your Project:

 

save and check in.png